Client
Kier Major Projects
Date of completion
May 2016
Value
£4.8m
Full Case Study Download
Groundworks scope
-
Installation of below ground drainage up to 8m depth
-
Installation of below ground tanks using an in-house designed cofferdam system up to 8m depth
-
Ground improvement works/stabilisation to circa 10,000m² of the site
-
Infrastructure works to the site perimeter including two roads constructed to adoptable standards
-
Construction of a 3,500m³ raft slab ranging from 600mm to 1m depth
-
The raft slab has circa 3,200m³ of concrete and aapproximately 250 tonnes of reinforcement
-
Installation of a new sub-station and accompanying services.
-
Construction of a 3,500m² ground level car park
-
Hard landscaping
Frame scope
-
The frame is split over three sections, blocks A to C and sequenced respectively
-
Each floor has a combined area of circa 3,500m² with slab depths ranging from 275mm to 350mm
-
Block A is a three-storey structure with a fourth floor constructed with a steel frame
-
Block B is a three-storey structure with a feature stair detail from the raft slab to the roof
-
Block C is a four-storey structure with a fifth floor constructed with a steel frame
-
There is circa 4,500m³ of concrete for the frame construction and around 550t of reinforcement