Client
F.B Ellmer Limited
Date of completion
March 2015
Value
£3m
Full Case Study Download
Scope of works
-
The conversion of Grade I listed building into 15 residential units with swimming pool, car parking and leisure facilities within new double basement
-
Piling
-
Demolition
Project key points
-
Installation of piles, stools and needles from within existing lower ground floor
-
Sheet piling using silent and vibrationless techniques
-
Piecemeal demolition of slabs and walls including all temporary works
-
Excavation of two-storey basement under existing building in top down fashion
-
Construction of RC works to form two levels of basement and new swimming pool
-
Re-construction of four-storey building including new slabs, walls and cores
-
Value engineered the scheme by replacing the piled raft with a ground bearing raft and the secant piles with sheet piles; saving the client cost and time