Client
Grove Developments
Date of completion
November 2017
Value
£23.1m
Full Case Study Download
Scope of works
-
Structural design
-
Sheet piling, reinforced concrete capping beam
-
Bulk excavation
-
Internal basement drainage
-
Reinforced concrete substructure (two floors)
-
Basement waterproofing; a cavity drain system with protective linear wall.
-
Reinforced concrete substructure (seven floors)
-
Twin wall and pre-cast columns
Project key points
-
Design and build to deliver the structure for a 755 bedroom hotel
-
Significant savings delivered to the client by value engineering the foundation solution
-
Two-level basement below ground
-
(Total basement area 10,500m²)
-
Seven-storey RC frame above ground floor
Contact Toureen Group
If you are looking for a contractor to undertake major projects, reinforced concrete frames and groundworks, please get in touch with us using the details on our contact page.